Town Green Improvements


Location: Town Center - 275 Broad St

Town Center - 275 Broad St

The Town Green Improvements project was proposed in order to eliminate safety concerns, improve handicap accessibility, and improve drainage and aesthetics.  This work will include replacing sidewalks and brick on the north-south sidewalk from J. Morrissey to Grace Church, replacing curbing sidewalk and brick along Broad street from the Luddy House to Batchelder Road, replacing the decorative street lights and placing the wiring in conduit, and repaving the roadway around Eagle Green.

Start Date : June 2007
Completion Date : September 2009
Cost : $507,380
Comments :

The project was completed over 3 construction seasons. The general contractors were GEG Construction, Clover Construction and Martin Laviero Contractors.