Mayor Trinks called the regular meeting to order at
7:33 p.m.
-
Roll Call – Present: Mayor Trinks, Deputy Mayor
Curtis, Councilor Broxterman, Councilor Ellingwood,
Councilor Dean, Councilor Jepsen, Councilor
Mulligan, Councilor Simon and Councilor Walker
-
Prayer – Councilor Mulligan
-
Pledge of Allegiance – Councilor Mulligan
-
Proclamations/Awards
None.
-
Public Communications and Petitions
Mr. George Yeramian, 739 Prospect Hill Road, spoke
to the Council regarding consideration of resuming the
acceptance of gypsum material at the Windsor –
Bloomfield Landfill. Although business was lost, he
noticed an increase in dumping of other materials. He
suggested using a cost incentive.
Mr. Patrick Terrion, 510 Hearthstone Drive,
addressed the Council regarding the landfill. He is
concerned about leaving the possibility open of
accepting gypsum from non-residents. In the budget,
the interest assuming to be earned is 3%, but costs go
up 3% with inflation. Every investment is designed to
exceed inflation. We continue to view this as a
revenue producing asset and it has been that way over
many years, but at this point, it is a liability. We
need to manage long term liability over profits. The
six-month window for accepting gypsum is not long
enough because of the odor problems that occur in the
fall. The current gas collection system should be
tested during a stressful situation to see if it
works.
- Report of Appointed Boards and Commissions
- Public Building Commission
Mr. Joseph Novak, Chair, reported to the Council.
WHS – The completion was accepted at their last
meeting.
Welch Pool Renovation – materials have been ordered
and work will continue in the spring.
Clover Street Window Replacement Project – Work
will begin in the fall of 2005. The PBC authorized the
staff and architect to put the project out to bid again.
Poquonock Office Improvements – complete. There are
a few minor change orders that will be closed out at the
next meeting.
Library Expansion Project – a contract was signed
last week with the low bidder. There were about four to
five additional alternatives reviewed and three of them
were approved. The approved alternatives were adding
handicapped bathrooms in the basement level, extra work
in the courtyard and replacing all of the windows. The
alternatives not approved were adding more pumps for a
spare and renovations to the Mallard House (which may be
able to be completed if there is any contingency left).
- Town Manager’s Report
Town Employee Recognized
It is always a pleasure to announce stellar
achievements made by town employees and I would like
to take a moment to recognize Anne Wakelin, who
manages the Windsor Discovery Center and Montessori
School. The Office of Graduate Studies at Central
Connecticut University recently notified Anne that she
would be the recipient of a $1,000 scholarship. This
academic award is given to deserving graduate students
who meet high academic standards set by the Graduate
Studies Committee. The committee noted that Ms.
Wakelin has achieved the highest standards of
excellence in her academic work. The scholarship
award, which will be presented at an Awards ceremony
at the University on February 10th, can be
applied toward future registration fees this spring or
summer semester. Congratulations to Anne.
Library Update
As you are probably aware, the library closed its
doors for business last Monday and will remain closed
until January 21st. At that time, the library will
re-open at its temporary location at 139 Broad Street
(the former Aglow Auction building.) Both the library
hours and their phone number will remain the same
while library services are provided from this
temporary location for approximately 16 months and
while renovations at the main library site are in
progress. As a reminder to library customers,
computers, fax machine and 30% of the library’s most
popular items will be available at the temporary
location. Book returns are available at both the main
library and at the temporary location until further
notice.
Ice Skating
The recent drop in temperature will surely heighten
awareness of ice skating opportunities in town. There
are three outdoor ice skating venues available for
skating in Windsor. When conditions are safe, enjoy
ice skating at Welch Park, Sharshon Park and the
Windsor Town Green. For current ice conditions, call
the recreation 24-hour information line at 285-1988.
Budget Public Hearing
By way of reminder to those in attendance and our
television audience, a public hearing will be held on
Monday, February 7, 2005 at 7:15 PM, here in the Town
Hall Council Chambers to hear citizen’s input on the
fiscal year 05/06 budget.
- Communication from Council Members
Councilor Broxterman – None.
Councilor Dean – None.
Councilor Ellingwood – None.
Councilor Jepsen – attended the forum sponsored by
Senator Coleman. Our recent creation of a Redevelopment
Agency was discussed. He noted that there are some
efforts to change some of the wording in the state
statute.
Councilor Simon – thanked Senator Coleman for
entertaining several members of Council and citizens to
provide comments for the upcoming legislative session.
The Metropolitan District Commission decided to create a
new $110,000 a year position for government lobbying. In
a time of fiscal restraint for every municipality, he
didn’t think that a new position should have been
added.
Councilor Mulligan – also thanked Senator Coleman
for having a forum. He didn’t receive his invitation
soon enough to attend the meeting
Councilor Walker – None.
Deputy Mayor Curtis – the Town Manager and staff
had an important opportunity to voice their comments for
the upcoming legislative session at the forum.
Mayor Trinks – thanked the Archer AME Church for
the Martin Luther King celebration. Congratulations to
ADVO. Senator Lieberman awarded them for their
partnership with National Exploited and Missing
Children.
- Reports of Standing Committees
-
Finance Committee - a meeting will be held Monday,
January 24, 2005.
-
Town Improvements Committee – None.
-
Health and Safety – None.
-
Special Projects – None.
-
Joint Board of Education and Town Council
Committee – None.
-
Personnel Committee – None.
- Ordinances
- Approve an ordinance entitled, "AN ORDINANCE
APPROPRIATING $445,000 FOR RECONSTRUCTION OF ELM
STREET FROM ITS INTERSECTION WITH BROAD STREET TO
ITS INTERSECTION WITH PRESTON STREET AND RELATED
AMENITIES AND IMPROVEMENTS INCLUDING SIDEWALK AND
CURBING INSTALLATION AND DRAINAGE IMPROVEMENTS AND
AUTHORIZING THE ISSUE OF $445,000 BONDS AND NOTES TO
FINANCE THE APPROPRIATION."
Resolved by Deputy Mayor Curtis, seconded by
Councilor Jepsen that the reading into the minutes of
the text of the ordinance entitled, "AN ORDINANCE
APPROPRIATING $445,000 FOR RECONSTRUCTION OF ELM STREET
FROM ITS INTERSECTION WITH BROAD STREET TO ITS
INTERSECTION WITH PRESTON STREET AND RELATED AMENITIES
AND IMPROVEMENTS INCLUDING SIDEWALK AND CURBING
INSTALLATION AND DRAINAGE IMPROVEMENTS, AND AUTHORIZING
THE ISSUE OF $445,000 BONDS AND NOTES TO FINANCE THE
APPROPRIATION" is hereby waived, the full text of
the ordinance having been distributed to each member of
the Council and copies being made available to those
persons attending this meeting; and that the full text
of the ordinance be recorded with the minutes of this
meeting.
Motion Passed 9-0-0
Councilor Simon asked about the bond process. Town
Manager Souza discussed the bond counsel and the
process, including legal costs and payment to the
Financial Advisor who assists in the selling of the
bonds.
Deputy Mayor Curtis thanked the Town for their work
in planning this project.
Councilor Jepsen asked about the storm drainage and
if it goes into the Creamery Brook. He also asked if the
Wetlands Commission has approved the plan. Mr. Tom
Lenehan, Town Engineer, said there is an existing
drainage right into the brook. It is possible that the
reconstruction will add a small incremental increase to
the brook. They are hoping to divert some of the
drainage. The Wetlands Commission has not approved this
yet. As part of the project, they will be fixing the end
wall to improve the town’s drainage system. Councilor
Jepsen asked if the Wetlands Commission has a problem
with the project, how will that affect the bond issue.
Town Manager Souza said that they would try to get
wetlands review prior to moving forward with the sale of
the bonds to minimize any issues that may arise.
Moved by Deputy Mayor Curtis, seconded by Councilor
Ellingwood that an ordinance entitled, "AN
ORDINANCE APPROPRIATING $445,000 FOR RECONSTRUCTION OF
ELM STREET FROM ITS INTERSECTION WITH BROAD STREET TO
ITS INTERSECTION WITH PRESTON STREET AND RELATED
AMENITIES AND IMPROVEMENTS INCLUDING SIDEWALK AND
CURBING INSTALLATION AND DRAINAGE IMPROVEMENTS, AND
AUTHORIZING THE ISSUE OF $445,000 BONDS AND NOTES TO
FINANCE THE APPROPRIATION " be approved.
Motion Passed 9-0-0
- Unfinished Business
- Discussion regarding the suspension of the
acceptance of gypsum material at Windsor-Bloomfield
Landfill
Moved by Councilor Jepsen, seconded by Councilor Dean
to accept pre-sorted construction and demolition
material, which removes significant quantities of gypsum
prior to disposal; and accept unsorted construction and
demolition material originating from the towns of
Windsor and Bloomfield; and continue the ban on gypsum
from all other sources.
Mr. Peter Souza, Town Manager, Mr. Brian Funk,
Director of Public Works and Mr. Mark Goossens, Solid
Waste Manager, gave an overview of the plan.
Councilor Ellingwood asked about the line for
contributions. Mr. Tom Lenehan, Town Engineer, stated
that it is growth in the fund. Councilor Ellingwood
asked what happens to the $13.5 million dollars. A
majority will be spent in FY 2008 and the remaining over
a two-year period with approval for closure from the
DEP.
Councilor Mulligan asked when we started filling the
wedge. Mr. Funk replied in 2000. We now have a gas
collection system in all areas where bulky waste is
collected. Councilor Mulligan noted the closure of the
system last week to replace a part and commented on the
noticeable odor. A comprehensive plan should also
include spare blowers or other parts onsite in case of
failure. Mr. Goossens said that we have spare parts
onsite as well as a storage trailer.
Councilor Simon inquired about the processing method
for screening out gypsum and if there are only two ways
to process bulky waste. Mr. Funk responded that Cherry
Hill does not separate gypsum. The other facility will
screen it out. The only other way would be to do it
manually. This option would allow bulky waste to be
brought to the landfill by Bloomfield-Windsor
contractors the same way it was prior to November 2004.
Mr. Goossens added that we are looking at other transfer
stations in the State to see who removes gypsum.
Councilor Simon asked why the difference in cost. Mr.
Funk said that the difference is for the costs of
removing the gypsum. We are in competition for this
material with facilities in Massachusetts and their
costs are in the same range. Councilor Simon asked when
we would have the State’s money in Windsor’s hands.
Mr. Funk replied that assuming the DEP’s process, by
the time of closure, no later than three years from now.
Councilor Walker commented that the gasses may be
getting trapped under the frozen surface. Perhaps we
would have a better feel for this in warmer weather. He
is not in support of this motion.
Councilor Dean asked for clarification on the bulky
waste pricing. She asked if we are undercutting everyone
else. Mr. Funk said that $45.00 for processed bulky
waste was charged to Cherry Hill. Town Manager Souza
said the pre-sorted price of $32.00 is in the market
place.
Councilor Mulligan has a problem with this motion. He
received correspondence from a DEP staff member when the
collection system was installed. The DEP staff member
made the statement that the situation would naturally
improve due to the time of year we are going into. We
are into the time of year where you wouldn’t expect to
have this problem. In the past, the problem occurred in
the fall. He has faith that the system we put in there
will solve the problem. He needs to see this go through
a full cycle, through the fall.
Councilor Broxterman asked if we can guarantee
citizens that bulky waste will not be placed anywhere we
don’t have a collection system. Mr. Funk said that at
this point, we don’t have plans to put bulky waste
where we have municipal solid waste (MSW), and per
regulations, we cannot put MSW in bulky waste areas.
Town Manager Souza added that the system expanded in
November covers the bulky waste cell and the wedge on
the southern most area of the landfill. We are expanding
vertically, not horizontally and bulky waste will only
be placed where there is a collection system. Councilor
Broxterman asked about the geo-membrane cap. Mr. Funk
said this system requires a geo-membrane cap, which is
more expensive than clay. It costs $3.5 to $4 million
for a clay cap and a geo-membrane is $3 to $4 million
more. The leachate management system ($1.1 million) is
proposed rather than a leachate collection system ($4.3
million). Councilor Broxterman asked if this proposal
provides space for Windsor-Bloomfield bulky waste to
come in as in the past. Mr. Funk responded that we would
stop the receipt of pre-sorted bulky waste prior to July
2007 so we would have room for Windsor-Bloomfield bulky
waste until closure. Councilor Broxterman asked if we
know of any higher standards from the DEP and he asked
if there is anything above the geo-membrane today. Mr.
Funk answered that the geo-membrane is the best there
is. Mr. Dave Hurley from Fuss & O’Neill added that
the DEP is looking at the 30-year mark. His advice is to
have the money in place to generate revenue to pay for
post-closure for thirty years. Those requirements are
going to get stricter.
Deputy Mayor Curtis asked if the motion passes would
the fine powdery gypsum be coming into Windsor. Mr. Funk
replied that it would not be coming in. This option
assumes that the Windsor-Bloomfield C&D would return
in the same specifications prior to November 1, 2004,
which included large and small pieces of sheet rock. We
believe that the odor problems resulted primarily from
the powdered gypsum because it degraded quickly. Town
Manager Souza said that when we deposited the Cherry
Hill material it was confined to a deeper wedge. Now it
will be closer to grade, which should have a more
positive effect.
Councilor Jepsen thanked the staff for a great
report. He said that we should probably turn back on the
Windsor-Bloomfield non-processed gypsum. It is almost to
the point where we are micro-managing the landfill.
Councilor Broxterman said the goal is not to pass
along any of the landfill closure costs to the residents
of Windsor. He is concerned about accepting
non-pulverized gypsum. He asked what does the State do,
how does it impact their approving the closure process.
Town Manager Souza said that we are governed by the
elevation. Mr. Hurley added that the State has
designated Windsor as an MSW site and wants the landfill
to close the bulky waste portion because it conflicts
with MSW. He thinks that the DEP will be reasonable.
Councilor Simon doesn’t like this idea. He thinks
we should remove the entire restriction on gypsum, that
is the reason we put in the gas collection system. The
odor problem is managed, not eliminated. He is concerned
that if this motion is defeated, we will be in a greater
financial hole than if we accept this motion. He is also
skeptical about relying on the State’s $2 million in
three years. He will end up supporting this motion
because he doesn’t want things getting worse in the
long run.
Councilor Ellingwood thanked the staff. As a Council
and Town, we did a good job of managing this problem.
Sometimes there is a tendency to over-engineer things.
It is time to let the staff handle the facility. We can’t
take all risk out of anything. He supports this motion.
There is too much financial risk if we don’t.
Mayor Trinks has the same faith in the staff that the
entire Council does. He thanked the entire staff for the
presentation. If we are going to entertain bringing back
gypsum to the landfill, this is the way to do it. His
hesitation is not a lack of faith in the staff or the
equipment. Our problems seem to exist when the seasons
change. He would like to see a little time pass before
we do this. What we will lose in the next several months
we can make up in investments.
Motion Failed 4-5-0 (Councilors Walker, Dean,
Mulligan, Broxterman and Mayor Trinks opposed)
- New Business
None.
- Resignations and Appointments
Moved by Deputy Mayor Curtis, seconded by Councilor
Broxterman to:
Item B: Appoint Nancy Casasanta to the
Commission on Aging and Handicapped as a
democratic member for a three year unexpired
term to expire January 31, 2005 or until a
successor is appointed
Item D: Reappoint Estelle LaBarre to the
Commission on Aging and Handicapped as a
democratic member for a three year unexpired
term to expire January 31, 2008 or until a
successor is appointed
Item F: Reappoint Linda Rickard to the
Commission on Aging & Handicapped as a
democratic member for a three year unexpired
term to expire January 31, 2008 or until a
successor is appointed
Item G: Reappoint Susan Viner to
Commission on Aging & Handicapped for a
three year unexpired term to expire January 31,
2008 or until a successor is appointed;
Item I: Reappoint Mark Griffin to the
Economic Development Commission as a democratic
member for a five year term to expire January
31, 2010 or until a successor is appointed
Item L: Appoint Ikesha Easterling to the
Fair Rent Commission as a democratic tenant
member for a three year unexpired term to expire
March 31, 2007 or until a successor is
appointed.
Motion Passed 9-0-0
- Minutes of Preceding Meetings
- Minutes of the January 3, 2005 Regular Town
Council Meeting
Moved by Councilor Broxterman, seconded by Councilor
Jepsen to accept the minutes of the January 3, 2005
Regular Town Council Meeting. Corrections: Page 6 –
Councilor Broxterman made a friendly amendment should be
Councilor Simon.
Motion Passed 9-0-0
- Public Communications and Petitions
None.
- Executive Session
None.
- Adjournment
Moved by Councilor Broxterman, seconded by Councilor
Jepsen to adjourn the Regular Town Council Meeting at
9:40 p.m.
Motion Passed 9-0-0
Respectfully submitted,
Kristin Countryman
Clerk of the Windsor Town Council
Cc: Town Clerk
Main Library
Wilson Branch